ACC Bank

DMG Engineering Ltd. was the Mechanical contractor for this project. The contract included for installation / modification to the following –

  • Disconnecting and strip out of 4nr existing McQuay chillers.
  • Installation of 2nr new Daikin Chillers.
  • Modifications to existing pipework and installation of new pipework.
  • Installation of insulation and cladding.
  • Installation of new twin head primary pump
  • Strip out and removal of existing Liebert units in comms room.
  • Installation of 4nr new Mitsubishi Electric split AC units in comms room.